USDA PHASE 1 SEWER EXPANSION PROJECT: RIVERSIDE DRIVE

TWWD has secured $7.1 million in federal grants and loans to expand the sewer infrastructure in Tiverton within the Riverside Drive and Robert Gray neighborhoods.   A map of the project areas is available herePhase 1 Project Map – Riverside & Robert Gray

Property owners had the opportunity to vote on the project. Ballots were opened and counted on June 15, 2015 at the North Tiverton Fire District Water Department Office. Voters approved the project overwhelmingly; by 65% in Riverside Drive and 87% in Robert Gray areas.

A full list of properties is available herePhase 1 Project Riverside and Robert Gray Property List

RIVERSIDE DRIVE AREA PROJECT INFORMATION
LOW PRESSURE SEWER
In 2015, the community voted to move forward with construction of a low pressure sewer system in the Riverside Drive area of Tiverton.  The system has been deemed the most cost effective and efficient way to provide sewer service to this area.  A low pressure sewer involves the installation of a grinder pump for each property.

The project will include both public right of way work for installation the sewer lines and curb to curb repaving as well as the necessary private property work to complete the connection to the building.  The project assessment is a not-to-exceed cost of $18,000 for all public and private property work.

Below are links to materials that were provided at the public education meetings.

RIVERSIDE DRIVE AREA PROJECT INFORMATION

Project Overview Sheet

Letter from Leroy Kendricks

Riverside Drive Presentation

Riverside Drive Cost Sheet

Wastewater Treatment Options Sheet

Grinder Pump FAQ – Riverside Only

Voting Process Sheet

Program Steps

  • Engineering , Design & Permitting

    Summer 2017

  • Bidding & Contract Award

    Fall 2017

  • Construction

    Spring 2018

Tie-In Requirements

If your property currently has an existing conforming system, and do not wish to tie in to the public sewer at the time of the project, under this new program you must….

Proximity

Pay for pipe in the street passing by your residence.

Inspection

Show proof when septic system was built and it must pass inspection.

Age

Have a system less than 25 years in service.

Duration

Have your residence tied in after 25 years of service.

Non-Conforming

Be tied in if a major improvement renders your existing system non-conforming.

Failure

Be tied in if your existing system fails.

Resources

Other sewer related resources.

Sewer Use Ordinance

Sewer Needs Map

Wastewater Facilities Plan Update

[/vc_column]
[/vc_column]
[/vc_column]
[/vc_column]

Contact Us

We're not around right now. But you can send us an email and we'll get back to you, asap.